|
Regulatory Branch
Our Mission
The primary goal of the Corps regulatory program is to protect the
nation's aquatic resources. This is accomplished through the issuance
of permits for projects that have undergone careful evaluation in
light of applicable laws, regulations and policy to insure that
no action authorized by our program will have an adverse impact
on the overall public welfare.
It is our mission to provide strong protection of the Nation's aquatic
environment, including wetlands; to enhance the efficiency of the Corps
administration of its regulatory program; and, to ensure that the Corps
provides the regulated public with fair and reasonable decisions.
|
|
|
Protecting our nation's aquatic environment.
|
Protecting public wetlands.
|
|
|
|
|
|
|
|
|
Wetlands
|
Wetlands are areas that are periodically or permanently inundated by
surface or ground water and support vegetation adapted for life in
saturated soil.
|
|
|
|
|
|
Wetlands serve important functions relating to fish and wildlife.
|
The Corps utilizes the 1987 Wetland Delineation Manual to identify wetlands
and define the physical boundary of our jurisdiction.
This manual outlines
the three essential parameters used to define a wetland:
|
|
|
|
|
|
Jurisdiction
|
The Corps derives it regulatory authority over waters of the United States
from the two Federal laws that are central to the Corps regulatory program.
Section 10 of the Rivers and Harbors Act of 1899 applies to all navigable
waters of the United States and Section 404 of the Clean Water Act applies
to all waters including wetlands that have sufficient nexus to interstate
commerce. Waters of the United States include essentially all surface waters
such as all navigable waters and their tributaries, all interstate waters
and their tributaries, all wetlands adjacent to these waters, and all
impoundments of these waters.
|
|
Determinations of Non-Jurisdiction for Isolated Waters
The Supreme Court's 2001 decision in the case of Solid Waste Agency of
Northern Cook County v. U.S. Army Corps of Engineers overturned the
Corps' assertion of federal jurisdiction over certain isolated wetlands
based on the presence of migratory birds. EPA and the Corps responded by
issuing revised guidance to their field offices. At the same time, the
Agencies reaffirmed federal jurisdiction over the majority of wetlands not
impacted by the decision.
|
|
|
|
|
How to Request a Jurisdictional Determination
|
In order to provide the most efficient service to the regulated community,
the Honolulu District recommends that applicants hire a recognized
environmental consultant to perform a preliminary determination of
jurisdiction. This applies to not only wetlands, but any feature that may
fall under the definition of a water of the U.S. as described above.
The Corps will then verify that the delineation is accurate and provide an
approved jurisdictional determination. Jurisdictional determinations are
generally valid for a period of five years, as site conditions and policies
can change. An interested party can request an updated determination at
any time.
|
|
|
|
|
Permit Requirements
|
Rivers & Harbors Act 1899 § 10
Section 10 of the Rivers and Harbors Act of 1899 requires approval prior
to the accomplishment of any work in or over navigable waters of the
United States, or which affects the course, location, condition or capacity
of such waters. Typical activities requiring Section 10 permits are:
-
Construction of piers, wharves, bulkheads, dolphins, marinas,
ramps, floats, intake structures, and cable or pipeline crossings.
-
Dredging and excavation
-
Artificial reefs
Clean Water Act - § 401 and § 404
Section 401 of the Clean Water Act requires that any applicant for a Federal
license or permit to conduct any activity including, but not limited to,
the construction or operation of facilities, which may result in any
discharge into the navigable waters, shall provide the licensing or permitting
agency a certification from the State in which the discharge originates that
any such discharge will comply with the applicable provisions of the Clean
Water Act.
Section 404 of the Clean Water Act requires approval prior to discharging
dredged or fill material into the waters of the United States.
-
Deposition (placement) of fill or dredged material in waters of the U.S. or
adjacent wetlands.
-
Site-development fill for residential, commercial, or recreational
developments.
-
Construction of revetments, groins, breakwaters, levees, dams, dikes,
and weirs.
-
Placement of riprap and road fills.
Coastal Zone Management Act - § 307
Section 307 of the Coastal Zone Management Act of 1972, as amended
(16 U.S.C. 1458(c)), requires the applicant certify that the project is in
compliance with an approved State Coastal Zone Management Program and
that the State concur with the applicants certification prior to the
issuance of a Corps permit.
Endangered Species Act - § 7
Section 7 of the Endangered Species Act of 1973 (ESA) requires Federal
agencies to ensure that any action authorized, funded or carried out by
them is not likely to jeopardize the continued existence of any endangered
or threatened species, or result in the destruction or adverse modification
of their critical habitat. Section 7 outlines the process for interagency
coordination by which the Corps consults with the United States Fish and
Wildlife Service (USFWS) and/or NOAA Fisheries on a proposed project's
potential to affect listed species.
National Historic Preservation Act - § 106
Section 106 of the National Historic Preservation Act (NHPA) requires that
the head of any Federal department, in this case, the Corps, having authority
to license any undertaking shall, prior to the issuance of any authorization,
take into account the effect of the undertaking on any district, site,
building, structure, or object that is included in or eligible for inclusion
in the National Register. Under Section 106 of the NHPA, the Corps is required
to consult with the State Historic Preservation Officer (an official appointed
in each State or territory to administer the National Historic Program)
in order to determine a project's potential to impact resources of historic
or cultural significance.
|
|
|
|
|
Types of Permits
Individual Permits
An Individual Permit is a type of Department of the Army authorization
that has undergone a full public interest review. This includes a 30-day
public notice period in which a copy of the permit drawings and a description
of the project are forwarded to all interested parties, adjacent property
owners, and the State and Federal agencies for review and comment.
Processing time for these types of permits is usually 60 to 120 days
from the receipt of a complete application for non-controversial projects.
Controversial or larger projects, including those that require a public
hearing or an Environmental Impact Statement (EIS), will generally take longer.
Letters of Permission
The Letter of Permission (LOP) is a type of individual permit used
in cases where the proposed project involves a lesser degree of impact
to aquatic resources. The LOP involves a 30-day comment period or a
15-day comment period in cases where the proposed impacts are minor
and non-controversial. State and Federal agencies and the adjacent
property owners are provided a project description and a copy of project plans.
A final decision on the LOP permit application is usually reached 45 to 60 days
from the date a complete application is received by the Corps' office.
Nationwide Permits
Nationwide permits are general permits issued nationwide to authorize
categories of minor activities. The Honolulu District has developed Regional
Conditions in order to provide additional protection for the aquatic
environment within the Pacific region. All persons wishing to perform work
under the nationwide permits must provide written notification to the Corps
prior to the start of work. The Regional Conditions provide a list of the
information necessary to submit a complete Pre-construction Notification (PCN).
After a review of the project, the Corps will issue a verification letter
pursuant to the applicable Nationwide Permit(s).
Regional General Permits
Regional General Permits are used to authorize activities that cause only
minimal individual and cumulative environmental impacts. Regional general
permits are developed by individual districts to streamline project review
by minimizing duplication of other federal, state and local review processes,
while still protecting aquatic resources. Regional general permits may be
restricted for use in areas as small as a single residential development,
a county, a region of the state or the entire district.
|
|
Public Notice:
2012 Nationwide Permit
Reissuance Request for Comments
The Corps of
Engineers Announces Final 2007 Nationwide Permits
|
|
|
Permit Process
|
Individual permit decisions are made within two to three months
from receipt of a complete application. In emergencies, decisions can be
made in a matter of hours. An emergency is a situation which would result
in an unacceptable hazard to life, a significant loss of property, or an
immediate, unforeseen, and significant economic hardship if corrective action
requiring a permit is not undertaken within a time period less than the
normal time needed to process the application under standard procedures.
Applications requiring review of endangered species, completion of an
Environmental Impact Statement or those experiencing other complications
will have a longer processing time. Complicating factors may include an
incomplete permit application, changes in the proposed project during
the evaluation process, substantial public opposition, or court decisions
which alter current case law.
|
|
|
|
|
Pre-Application Consultation
|
Since two to three months is normally required to process a routine
application involving a public notice, you should apply as early as
possible to be sure you have all required approvals before your planned
commencement date.
For a large or complex activity that may take longer,
it is often helpful to have a pre-application consultation or informal
meeting with the Corps during the early planning phase of your project.
You may receive helpful information at this point which could prevent
delays later.
Pre-application consultation usually involves one or several
meetings between an applicant, Corps district staff, interested resource
agencies (Federal, State, or local), and sometimes the interested public.
The purpose of such meetings is to provide for informal discussions
about the pros and cons of a proposal before an applicant makes irreversible
commitments of resources (funds, detailed designs, etc.).
The process is designed to provide the applicant with an assessment of
the viability of some of the more obvious alternatives available to
accomplish the project purpose, to discuss measures for reducing the
impacts of the project, and to inform him of the factors the Corps must
consider in its decision making process.
|
|
|
|
|
Public Interest Review
|
In its project evaluation process, the Corps must balance the project
purpose against the public interest, as required by the National
Environmental Policy Act (NEPA) of 1969. The public benefits and detriments
of all factors relevant to each case are carefully evaluated and balanced.
Relevant factors may include conservation, economics, aesthetics, wetlands,
cultural values, navigation, fish and wildlife values, water supply, water
quality, and any other factors judged important to the needs and welfare
of the people. The following general criteria are considered in evaluating
all applications:
-
The relevant extent of public and private needs
-
Where unresolved conflicts of resource use exist, the practicability of
using reasonable alternative locations and methods to accomplish project
purposes; and
-
The extent and permanence of the beneficial and/or detrimental effects
the proposed project may have on public and private uses to which the
area is suited.
No permit is granted if the proposal is found to be contrary to the
public interest.
|
|
|
|
|
Apply for a Permit

|
To aid applicants in submitting a complete application, Honolulu
District has developed a questionnaire to supplement the application
form. Application packages can be mailed directly to our offices in
Honolulu or Guam.
Federal, state and local agencies often have regulatory jurisdiction
over the same projects the Corps regulates. The Corps works
closely with applicable agencies to provide a consistent, coordinated
review of projects.
|
|
|
|
|
Administrative Appeals Process
|
The purpose of this Part is to establish policies and procedures to
be used for the administrative appeal of permit applications denied
with prejudice, and for the administrative appeals of declined individual
permits. The appeal process will allow the affected party to pursue
an administrative appeal of certain final Corps of Engineers decision
with which they disagree. The basis for an appeal, and the specific
policies and procedures are described in detail at the "33 CFR Part 331 -
Appeals Process" link to the right. It is the policy of the Corps of
Engineers to promote and maintain an administrative appeal process
that is independent, objective, fair, prompt, and efficient.
|
|
|
|
|
Mitigation
|
The Corps reviews each project application for its potential to
adversely impact aquatic resources. On June 10, 2008, the Final
Rule for Compensatory Mitigation for Losses to Aquatic Resources
(the Mitigation Rule) went into effect. The Mitigation Rule
clarifies what must be considered and what information is required
when developing compensatory mitigation for unavoidable impacts to
the nation’s aquatic resources, including wetlands, streams, and
ocean waters. When mitigation is required remains unchanged. The
Mitigation Rule also stresses that impacts must be avoided and
minimized, in that order, prior to the development of a compensatory
mitigation plan to offset permitted impacts.
***Each permit application must contain a statement on how the
project avoids, minimizes, and compensates for proposed adverse
impacts to aquatic resources***
In addition to the Rule, projects that require the discharge of
dredged or fill material into waters of the U.S. as regulated under
Section 404 of the Clean Water Act, must comply with the Section
404(b)(1) Guidelines (Guidelines). The Guidelines only allow the
Corps to authorize the least environmentally damaging practicable
alternative to achieving the project purpose.
Links to the Mitigation Rule and the Guidelines can be found in the
column to the right.
|
|
|
|
|
Enforcement
Involvement
When a project receives a permit from the Corps of Engineers, it
will be conditioned to allow representatives from the Corps of
Engineers to inspect the authorized activity and any mitigation,
preservation, or avoidance areas at any time deemed necessary to
ensure that the project meets the terms and conditions of the
permit. In addition to site inspections conducted by its staff,
the Corps relies on members of the public and representatives of
state, local, and other Federal agencies to report suspected
violations.
The Corps is required to take steps to investigate suspected
violations in a timely manner. The scheduling of investigations
will reflect the nature and location of the suspected violations,
the anticipated impacts, and the most effective use of inspection
resources available.
Activities performed without
required Department of the Army permits and activities not in
compliance with the terms and conditions of issued Department
of the Army permits are subject to enforcement action by the
Corps of Engineers. See the complete text of 33 CFR Part 326
regarding enforcement.
Violations
If you suspect a violation please contact us.
Violators may be subject to penalties, including fines up to $25,000
per day of violation, and/or orders to remove unauthorized fill and
to restore the area to pre-project conditions. For unauthorized work
conducted under the RHA, criminal penalties may be imposed up to
$100,000 in fines and up to one year imprisonment or both. Injunctive
relief, including restoration, is also available. Further, knowing
violations of Section 404 may be referred to the U.S. Environmental
Protection Agency for enforcement action.
|
|
|
|
|
|