Jump To

Public Notices

POH-2014-00209

Published Jan. 17, 2017
Expiration date: 2/3/2017

                                                           FEDERAL PUBLIC NOTICE

Interested parties are hereby notified that an application has been received for a Department of the Army permit for certain work in waters of the United States as described below and shown on the attached drawings.

APPLICANT:
Department of the Navy
Mr. Edward E. Moon, Environmental Director
NAVFAC PWD, Naval Base Guam
PSC 455, Box 195
FPO AP 96540

AGENT:
Ms. Leslie Robinson
Department of the Navy
NAVFAC Pacific, Environmental Compliance, EV1
258 Makalapa Drive, Suite 100
JBPHH, HI 96860-3134

WATERWAY AND LOCATION OF THE PROPOSED WORK:
The proposed project is located in Inner Apra Harbor at X-Ray Wharf on Naval Base Guam, in Santa Rita, Guam. The proposed dredged material disposal site is located at the USEPA designated Guam Deep Ocean Disposal Site (GDODS) which is located in the Pacific Ocean with a 3 nm boundary diameter located 11 nm west of Apra Harbor, Guam; centered at 13° 35.500’ N., 144° 28.733’ E.

PROPOSED PROJECT AND PURPOSE:
The Department of the Navy (Navy) is requesting a modification of Department of the Army (DA) permit No. POH-2014-00209 for the military construction (MILCON) project P-518 X-Ray Wharf Improvements Berth 1 to rehabilitate and modernize Berth 1 of the existing X-Ray Wharf in Inner Apra Harbor on Naval Base Guam.

The Navy is requesting an increase to the authorized construction dredging volume and area for the P-518 project. The overall dredging footprint remains unchanged, but four additional areas within the approach channel and turning basin/berth areas require dredging as identified during an August 2016 pre-dredge hydrographic survey.
The permit modification would add an estimated 79,540 cubic yards (CY), including a -2.0 feet of overdredge allowance, of dredging to the originally permitted volume of 51,000 CY to achieve a -35.0 feet mean lower low water (MLLW) navigational depth in the project footprint. Additionally, as a result of the August 2016 pre-dredge hydrographic survey, the permitted volumes were revised to approximately 37,580 CY from the authorized 51,000 CY. Therefore, the total volume of material to be dredged will be approximately 116,120 CY, including a -2.0 feet of overdredge allowance. All off the dredged material has been determined suitable for disposal at the Guam Deep Ocean Disposal Site (GDODS), as originally permitted. The new dredging locations will not impact any special aquatic sites, including coral reefs. The details of the permit modification request can be viewed in Enclosure 1.

AUTHORITY: A Department of the Army permit is required pursuant to:
X      Section 10 of the Rivers and Harbors Act of 1899 (33 U.S.C. 403) - To perform work in or affecting navigable waters of the United States.
         Section 404 of the Clean Water Act (33 U.S.C. 1344) - Discharge dredged or fill material into waters of the United States. The Corps’ public interest review will consider the guidelines set forth under Section 404(b) of the Clean Water Act (40 CFR 230).
X       Section 103 of the Marine Protection, Research and Sanctuaries Act of 1972 (33 U.S.C. 1413) - Transport dredged material for the purpose of dumping it into ocean waters. The Corps’ public interest review will consider the criteria established under authority of Section 102(a) of the Marine Protection, Research and Sanctuaries Act of 1972, as amended (40 CFR Parts 220 to 229), as appropriate.

WATER QUALITY CERTIFICATION:
On December 18, 2014, the Guam Environmental Protection Agency (Guam EPA) issued a Section 401 of the Clean Water Act (Public Law 95-217) Water Quality Certification (WQC) for the authorized project.

The Navy, as the lead federal agency, requested a water quality certification modification from Guam EPA on January 12, 2017. A final DA permit will not be authorized until a copy of the WQC modification is received.

COASTAL ZONE MANAGEMENT ACT CERTIFICATION:
On February 25, 2014, the Guam Bureau of Statistics and Plans, Guam Coastal Management Program (GBSP-CMP), concurred with the Navy’s determination under 15 CFR 930.35 that the authorized project would not have foreseeable coastal effects to Guam’s defined coastal zone, in accordance with Section 307(c)(3) of the Coastal Zone Management Act of 1972 (Public Law 92-583), as amended (16 U.S.C. 1456(c)(3)).

The Navy, as the lead federal agency, determined that proposed modification has no additional effects on any coastal use or resource, and an additional negative determination under 15 CFR 930.35 is not required. Guam BSP-CMP was notified of this decision by a letter dated December 28, 2016.

CULTURAL RESOURCES:
On December 7, 2011, the Guam State Historic Preservation Officer (SHPO) concurred with the Navy’s determination of “No Historic Properties Affected”. The July 2008 Programmatic Agreement among the Commander, Navy Region Marianas, Advisory Council on Historic Preservation, and the Guam Historic Preservation Office regarding Navy Undertakings on the Island of Guam describes processes to be followed in the event of inadvertent discoveries of historic properties during ground disturbing activities.

As the lead federal agency, the Navy is responsible for compliance with Section 106 of the National Historic Preservation Act (NHPA). On December 29, 2016, the Navy provided the following statement to justify their decision that no further consultation with the SHPO would be required for the proposed modification: The April 2014 Final Environmental Assessment addresses the impacts of MILCON project P-518, X-Ray Wharf Improvements Berth 1 and contains the consultations for Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act (ESA), and the Essential Fish Habitat (EFH) provision §305(b) of the Magnuson-Stevens Fishery Conservation and Management Act. The Section 106 consultation was based on a previous dredge footprint for the P-518 project that was larger than the current P-518 dredge footprint. As a result, all the consultations were based on a proposed total dredge quantity of 103,500 CY. This permit modification request does not change the P-518 dredge footprint. Rather, this modification request is to increase the required dredging volume to a total quantity of 116,120 CY. The Section 106 consultation was not reopened for this modification because the P-518 dredge footprint is still smaller than the project area that was consulted on previously. Therefore, the area of potential effect for Section 106 has not increased.

Therefore, the Corps do not intend to provide conduct any additional consultation with the Guam SHPO for this proposed modification in conjunction with this public notice.

ENDANGERED SPECIES:
Pursuant to Section 7 of the Endangered Species Act (ESA), federal agencies must consult with the National Marine Fisheries Service (NMFS) and/or U.S. Fish and Wildlife Service (USFWS) on any action that may affect a species listed (or proposed for listing) under the ESA as threatened or endangered or any designated critical habitat. Based on the project location, the following protected Near Shore Marine Species (NMFS jurisdiction) have the potential to occur near the project location: Green Sea Turtle (Chelonia mydas), Central West Pacific DPS, endangered; Hawksbill sea turtle (Eretmochelys imbricata), endangered; and Indo-West Pacific DPS Scalloped Hammerhead shark (Sphyrna lewini), threatened.

As the lead federal agency, the Navy is responsible for compliance with Section 7 of the ESA. On December 29, 2016, the Navy provided the following statement to justify their decision that no further consultation with NMFS or USFWS would be required for the proposed modification: The April 2014 Final Environmental Assessment addresses the impacts of MILCON project P-518, X-Ray Wharf Improvements Berth 1 and contains the consultations for Section 106 of the National Historic Preservation Act, Section 7 of the Endangered Species Act (ESA), and the Essential Fish Habitat (EFH) provision §305(b) of the Magnuson-Stevens Fishery Conservation and Management Act. The ESA consultation was based on a previous dredge footprint for the P-518 project that was larger than the current P-518 dredge footprint. As a result, all the consultations were based on a proposed total dredge quantity of 103,500 CY. This permit modification request does not change the P-518 dredge footprint. Rather, this modification request is to increase the required dredging volume to a total quantity of 116,120 CY. The ESA consultation was not reopened for this modification because the P-518 dredge footprint is still smaller than the project area that was consulted on previously. Therefore, the action area for ESA have not increased.

Therefore, the Corps do not intend to provide conduct any additional consultations with the NMFS or USFWS for this proposed modification in conjunction with this public notice.

ESSENTIAL FISH HABITAT:
The proposed work is being evaluated for possible effects to Essential Fish Habitat (EFH) pursuant to The Magnuson-Stevens Fishery Conservation and Management Act (MSA), as amended by the Sustainable Fisheries Act of 1996 (Public Law 104-267), which requires all Federal agencies to consult with the National Marine Fisheries Service on all actions, or proposed actions, permitted, funded, or undertaken by the agency, that may adversely affect Essential Fish Habitat. The Honolulu District includes areas of EFH as Fishery Management Plans.

As the lead federal agency, the Navy is responsible for compliance with MSA. On December 29, 2016, the Navy provided the following statement to justify their decision that no further consultation with the NMFS is required for the proposed modification: The April 2014 Final Environmental Assessment addresses the impacts of MILCON project P-518, X-Ray Wharf Improvements Berth 1 and contains the consultations for the Essential Fish Habitat (EFH) provision §305(b) of the Magnuson-Stevens Fishery Conservation and Management Act. The EFH consultation was based on a previous dredge footprint for the P-518 project that was larger than the current P-518 dredge footprint. As a result, all the consultations were based on a proposed total dredge quantity of 103,500 CY. This permit modification request does not change the P-518 dredge footprint. Rather, this modification request is to increase the required dredging volume to a total quantity of 116,120 CY. The EFH consultation was not reopened for this modification because the P-518 dredge footprint is still smaller than the project area that was consulted on previously. Therefore, the area of potential effect for the action area for EFH have not increased.

Therefore, the Corps do not intend to provide conduct any additional consultation with the NMFS for this proposed modification in conjunction with this public notice.

FEDERAL EVALUATION OF APPLICATION:
The decision whether to issue a permit will be based on an evaluation of the probable impact including cumulative impacts of the proposed activity on the public interest. That decision will reflect the national concern for both protection and utilization of important resources. The benefit which reasonably may be expected to accrue from the proposal must be balanced against its reasonably foreseeable detriments. All factors which may be relevant to the proposal will be considered including the cumulative effects thereof; among those are conservation, economics, aesthetics, general environmental concerns, wetlands, historic properties, fish and wildlife values, flood hazards, floodplain values, land use, navigation, shoreline erosion and accretion, recreation, water supply and conservation, water quality, energy needs, safety, food and fiber production, mineral needs, considerations of property ownership and, in general, the needs and welfare of the people.

The Corps of Engineers is soliciting comments from the public; Federal, state, and local agencies and officials; Indian Tribes; and other interested parties in order to evaluate the direct, indirect, and cumulative impacts of this proposed activity. Any comments received will be considered by the Corps of Engineers to determine whether to issue, modify, condition or deny a permit for this proposal. To make this decision, comments are used to assess impacts on endangered species, historic properties, water quality, general environmental effects, and the other public interest factors listed above.

PUBLIC HEARING:
Comments are also used to determine the need for a public hearing and to determine the overall public interest of the proposed activity. Any person may request, in writing, within the comment period specified in this notice, that a public hearing be held to consider this application. Requests for public hearings shall state clearly and concisely, the reasons and rationale for holding a public hearing. The District Commander will then decide if a hearing should be held.

COMMENT AND REVIEW PERIOD:
Comments on this public notice should be made in writing via conventional mail or e-mail. Comments will be accepted and made part of the record and will be considered in determining whether it would be in the public interest to authorize this proposal. Conventional mail comments should be sent to

Ms. Katy R. Damico
US Army Corps of Engineers, Honolulu District
Guam Regulatory Field Office
PSC 455 Box 188
FPO, AP 96540-1088

Alternatively, comments may be emailed to Katy.R.Damico@usace.army.mil. Reference POH-2014-00209 in the subject heading of the email. In order to be accepted, e-mail comments must originate from the author’s e-mail account.

Both conventional mail and e-mail comments must include the DA permit number POH-2014-00209, and the commenter’s name, address, and phone number. All comments whether conventional mail or e-mail should be received by the close of business on FEBRUARY 3, 2017.

PRIVACY & CONFIDENTIALITY:
It should be noted that materials submitted as part of the permit application become part of the public record and are thus available to the general public under the procedures of the Freedom of Information Act (FOIA). Submissions should not include any information that the submitter seeks to preserve as confidential.

If you have any questions about this project or the permit process, please contact
Ms. Katy Damico of the Guam Regulatory Field Office via telephone at (671) 339-2108 or (808) 835-4160 or via email at Katy.R.Damico@usace.army.mil.

 


Contact Information

Honolulu District Public Affairs
Building 230
Fort Shafter, Hawaii 96858-5440
(808) 835-4003
CEPOH-PA@usace.army.mil 

Regulatory Office
Building 252
Fort Shafter, HI  96858-5440
(808) 835-4303
CEPOH-RO@usace.army.mil 

FUDS Office
Building 230
Fort Shafter, Hawaii 96858-5440
(808) 835-4084
HonoluluDistrictFUDSInfo@usace.army.mil

Guam Field Office
Apra Harbor Naval Complex
PSC 455 Box 188
FPO, AP 96540-1088  Guam
(671) 339-2108 
CEPOH-RO@usace.army.mil

Civil and Public Works Branch

Civil and Public Works Branch

Bldg. 230 Fort Shafter, HI 96858